bombardier

Installation of Bombardier’s Automatic People Mover at King Abdulaziz International Airport in Jeddah ARC undertook the Electrical & Mechanical Installation of the Bombardier Automatic People Mover at King Abdulaziz International Airport (KAIA) in Jeddah our scope of work included the followings:

• Installation of the following systems:

• CBTC Signalling System,

• OCC Installation,

• Fiber Optic Network,

• Telecoms,

• Access Control & Security Systems,

• Traction Power System,

• 3rd Rail Conductor System,

• UPS Equipment,

• Depot Equipment Installation,

• Creation of Installation Design from Concept Design

• Procurement of material

• Gaining of Approval from Consultants The scope of work meant at the peak of the installation we had a team of over 100 qualified engineers, technicians working on this project.